Posted 21 June 2017 by Ofgem in Policy, Regulation and Strategy

View this item

Following our March consultation, having taken into account all responses to our impact assessment and our open letters and having carried out further modelling, the Authority decided to confirm our “minded to” position and direct that Workgroup Alternative CUSC Modification (WACM) 4 should be made. These matters were considered by the Authority on 15 June 2017. WACM 4 removes the TNUoS Demand Residual (TDR) payments to smaller EG and introduces a new payment (equivalent to the avoided GSP costs), introducing the changes through a three-year phased implementation, beginning on 1 April 2018.